After 2 days of of the foreman going AWOL (whom by the way is the son in law) they decided that to finish off the roof they would instead pay another relative to complete the task. Well on that morning the son in law turned up so they completed the roof structure together and got on with fastening on most of the corrugated iron sheets.
Here's mixer again modelling his Thai TV show shirt and lots of talcum powder on his face.


So this is the day after they almost completed the roof (they need 5 more corrugated iron sheets) and its now Songkran (Thai new year). You can see them building a temporary shelf and moving in a table because they want to sell noodles and drinks during this holiday period. There will be no progress during this three day water fight new year party and it wont be until the 16th of April that they will continue.


So this is the temporary shelf with all the drinks on and the noodles being heated ready for the day ahead.